February 27, 2026
Author : Patty Allen
Construction of the Capitol Annex Project in California is over half completed. Thus far, $573.8 million has been spent as state officials work toward their 2027 completion date, despite cost increases, schedule adjustments, and complex renovation challenges.
Those leading the project say the milestone is indicative of the steady progress of probably one of the largest public construction undertakings statewide. However, the continuation of inflation, the complexity of the design, and phased construction remain challenges for the project budget and timeline.
According to the latest official Q&A for the project, physical works are underway on the main structural, mechanical, and seismic upgrades of the historically significant Capitol Annex building. The refurbishment is aimed at raising the level of safety, accessibility, and energy efficiency, as well as the long-term functionality of lawmakers and staff, while preserving the building's historic character.
Those leading the project are pointing out that the sequencing of construction has been very complicated, particularly because government premises must remain fully operational.
The price increases have been caused by a combination of factors, including inflation, more stringent building code requirements, and the broader scope linked to safety and systems upgrades.
Lawmakers have recognized that, even though the project's cost is rising beyond initial estimates, it remains a long-term investment aimed at extending the life of the Capitol complex for decades. State officials are still stressing the importance of oversight and cost-saving measures as the work moves closer to completion.
The Capitol Annex project is part of a broader national trend in which the government is spending heavily on renovating its facilities. This is happening at the same time as the old legislative buildings all over the country need to be modernized due to wear and tear. Other similar projects in different states, such as similar major renovations, have also experienced the same problems: huge budget blowouts and considerable schedule delays.
The project has highlighted the importance of inclusive procurement. Officials have pointed to the participation of states' Disabled Veteran Business Enterprises (DVBE) program as playing a direct role in assisting large public works projects, thereby demonstrating how long-term government construction can lead to positive economic ripple effects.
Construction on the Capitol Annex was initially part of a $1.2 billion redevelopment plan for the Sacramento complex, making the project among the largest state government construction efforts in California history.
State officials say the main focus will remain on maintaining momentum, controlling costs, and providing a modernized Capitol Annex that can accommodate California's legislative operations well past 2027, with the project now half done.